Clean Room area: 4360M²
Cleanliness level: CLASS 1K
Project Description:
· Clean Room system installation
· Installation of purification air conditioning system (water system/air system)
· PCW process cooling water system installation
· CDA/N2 piping system installation
· Electrical system and UPS installation
· Power station air compressor and vacuum system installation
· Secondary configuration of equipment
Project time: 2017.04