Shanghai Macproc Engineering Technology Co., Ltd.

Project Cases Ⅳ

    详细说明

    Clean Room area: 3100M²
    Cleanliness level: CLASS 1K
    Project Description:
    · DB/WB Clean Room system installation
    · Installation of purification air conditioning system (water system/air system)
    · PCW process cooling water system installation
    · CDA/N2 piping system installation
    · Electrical system and UPS installation
    · Power station air compressor system installation
    · BMS system integration
    · Secondary configuration of equipment
    Project time: 2012.05

    Write To Us

    Please fill out the form and your request will be answered within one working day.

    previous item: Project Case Ⅱ next item: Project Cases Ⅷ